Centennial Corridor


View flyover video of the Centennial Corridor alignment
Click here to view previous flyover 

Project Description:
The Centennial Corridor Project will construct a new alignment and provide route continuity and traffic congestion relief for State Route 58 from Cottonwood Road on existing State Route 58 (East) to Interstate 5. 

Project Status:
Phases 1, 2 and 3 are under construction. Phase 4 has been advertised for construction bids. 

Centennial Corridor Phase 1 - Kern River Bridge Improvements Projecis under construction.

Centennial Corridor Phase 2 - Belle Terrace Operational Improvements demolishes the existing Belle Terrace Overcrossing and replaces it with a structure that meets current vertical clearance requirements. This phase also improves northbound State Route 99 to eastbound State Route 58 traffic flow by reconstructing the connector structure over Wible Road and widening it to two lanes. Wible Road and Alamo Court will be realigned with the project. This phase is under construction.

Centennial Corridor Phase 3 - Bakersfield Freeway Connector reconstructs the westbound-to-southbound loop ramp at the State Route 58/State Route 99 interchange. The project constructs an auxiliary lane on westbound State Route 58 and widens the westbound bridge crossing State Route 99. This phase addresses bottleneck congestion on southbound State Route 99 by separating freeway on- and off-ramps between State Route 58 and Ming Avenue. The eastbound and westbound State Route 58 connectors will be combined into one branch connecting to southbound State Route 99. The entrance to the Ming Avenue off-ramp will be moved north and motorists will travel on a barrier-separated connector to Ming Avenue. This phase is under construction.

Centennial Corridor Phase 4 - Mainline & SR 58/SR 99 Ramp Connectors - will construct the freeway and structures between State Route 99 and the Westside Parkway. Phase 4 will also construct the northbound-to-westbound connector ramp at the State Route 58/State Route 99 interchange. In June 2018, Congressman Kevin McCarthy notified the City that the US Department of Transportation intends to award $50 million through the Infrastructure for Rebuilding American (INFRA) program for the completion of Centennial Corridor. Project has been advertised for construction bids. Anticipated construction start: mid-2019. 

Caltrans and the City of Bakersfield have implemented a Voluntary Emission Reduction Agreement with the San Joaquin Valley Air Pollution Control District to provide mitigation measures that benefit residents living adjacent to the future Centennial Corridor Project. Residents and property owners may qualify for rebates to replace wood burning stoves and open-hearth fireplaces with cleaner alternatives. Visit the Valley Air website for information and guidelines on how to participate in the Burn Cleaner program.

Centennial Corridor Construction Phases Map

Screen Wall Location Maps
Screen wall locations between California Avenue and Stockdale Highway
Screen wall locations south of Stockdale Highway

Centennial Corridor Community Meeting Exhibits
Centennial Corridor Map - Grade Distinctions - State Route 99 to Stockdale Highway
Centennial Corridor Map - Grade Distinctions - Stockdale Highway to California Avenue
Centennial Corridor Map - Sewer Realignment - State Route 99 to Stockdale Highway
Centennial Corridor Map - Sewer Realignment - Stockdale Hwy to California Avenue
Centennial Corridor Map - Walls & Cul-de-sacs - State Route 99 to Stockdale Highway
Centennial Corridor Map - Walls & Cul-de-sacs - Stockdale Hwy to California Ave. 2018
Centennial Corridor Map - Bike Path
Centennial Corridor Sound Wall Aesthetic Themes

Documents

Record of Decision
Final Environmental Impact Report/Environmental Impact Statement Volume 1
Final Environmental Impact Report/Environmental Impact Statement Volume 2
Final Environmental Impact Report/Environmental Impact Statement Volume 3
Findings for Centennial Corridor Project
Statement of Overriding Consideration
Final Project Report Signed - November 2015


Maps
 

Alternative B Westpark Exhibit
Alternative B State Route 58 Exhibit
(These maps were presented at the Public Hearing held on June 11, 2014)


Technical Reports
 

Aerially Deposited Lead Investigation
Aerially Deposited Lead Investigation Addendum

Air Quality Study Report
Air Quality Study Report Addendum

Archaeological Survey Report

Biological Assessment
Biological Assessment Addendum

Community Impact Assessment

Extended Phase I Geoarchaeological Report: Stage 1

Extended Phase I Geoarchaeological Report: Stage 1 Transmittal Letter

Extended Phase I, Stage II Geoarchaeological Investigations

Final Relocation Impact Report

Finding of Effect

Focused Initial Site Assessment

Historic Property Survey Report

Historic Property Survey Report Supplemental

Historic Resources Evaluation Report

Initial Site Assessment

Jurisdictional Delineation

Location Hydraulic Study

Natural Environment Study

Noise Abatement Decision Report

Noise Study Report

Noise Study Report Addendum

Noise Study Report and Noise Abatement Decision Report Addendum

Paleontological Evaluation Report

Paleontological Evaluation Report Addendum

Preliminary Geotechnical Report Addendum

Preliminary Site Investigation - Acquisition Property Soil

Preliminary Site Investigation Asbestos and Lead_Based Paint Survey

Traffic Study Volume I

Traffic Study Volume II (1 of 2)

Traffic Study Volume II (2 of 2)

Traffic Study Addendum

Visual Impact Assessment

Visual Impact Assessment Addendum

Water Quality Assessment Report

Water Quality Assessment Report Addendum

 

Related Information and Documents

Caltrans Project Contacts
Community Cohesion Mitigation Plan
Westpark Multiuse Path Network Proposal
Regional Transportation Plan
Federal Transportation Improvement Plan
San Joaquin Valley Interregional Goods Movement Plan
California Freight Mobility Plan
National Freight Strategic Plan
2013 California State Rail Plan
Articles from The Bakersfield Californian
National Significance Map
Project Segment Map
Centennial Corridor Draft Financial Plan Annual Update
Centennial Corridor Cost Estimate Review
Benefit Cost Analysis_Connector-Mainline
Centennial Corridor Permits and Approvals
Centennial Corridor Risks and Mitigation Strategies
INFRA Support Letters
For additional information visit California Department of Transportation project site.